Third Party Inspection for Gas Circuit Breaker

The Third Party Inspection for Gas Circuit Breaker provides you with information about the gas circuit breaker test and gas circuit breaker inspection in the manufacturing shop.

You may need to review this article along with the following article:

Inspection and Test Plan for Gas Circuit Breaker

This content guides you through all the necessary stages in the production of the gas circuit breakers , including the raw material, final inspection, preservation and packing, and dispatch to site.

You need to take this point into account: this article is written for a typical gas circuit breaker and might not be detailed for special cases.

This content may be useful for second party inspectors, gas circuit breaker manufacturer quality control personnel, engineering companies, and purchasers, as well.

All gas circuit breaker inspection and testing is done against the approved drawings, purchase order specifications, purchasers or company standards, and within the practices and rules of the country, state or province and any government decrees, laws, ordinance or regulation as may apply.

The applicable codes and specifications for a gas circuit breaker that is under the construction process is:

  • Design code
  • Purchase order specification
  • Purchaser's standards
  • Approved drawings

The applicable codes and standards may be based on any international standards. This content is general and can be useful for all recognized standards.

Required Documents for Third Party Inspector Review:

The list of documents normally is agreed upon in the Pre-Inspection meeting, which is held several weeks before the actual commencement of the inspection work. The parties that participate in this meeting are the manufacturer, purchaser and third party inspection agency representatives.

This is already explained in the Inspection and Test Plan for Gas Circuit Breaker article.

These are the list of documents that are normally agreed upon to be presented to the inspector:

  • Gas Circuit Breaker Purchase Order or Contract
  • Gas Circuit Breaker Manufacture Quality Control Plan
  • Gas Circuit Breaker Inspection and Test Plan
  • Gas Circuit Breaker Data Sheet
  • Gas Circuit Breaker Approved Drawings, (arrangements, schematics, wiring, single line)
  • Gas Circuit Breaker Gas Circuit Breaker Material Test Reports
  • Gas Circuit Breaker Welding Specification Procedures (WPS) and Procedure Qualification Records(PQR)
  • Gas Circuit Breaker Welders Qualifications Reports
  • Gas Circuit Breaker Calibration Certificates for Test Equipment
  • Gas Circuit Breaker Special Procedures
  • Gas Circuit Breaker Special Qualifications
  • Gas Circuit Breaker Preparation and Painting Procedure
  • Gas Circuit Breaker Preservation, Packing and Shipping Procedure
  • Gas Circuit Breaker Packing List

Third Party Inspection for Gas Circuit Breaker-Material Inspection

The first actual inspection work in the gas circuit breaker is the raw materials inspection.

The original or authenticated copies of mill certificates of material normally are available at the manufacturer's premises.

The third party inspector examines these certificates for compliance with specifications, and where appropriate, drawings.

The review includes checks on:

  • Certificate No.
  • Heat or cast No.
  • Chemical composition.
  • Mechanical properties.
  • Heat treated condition.
  • NDE applied and results.
  • Surface finish

Then the inspector witnesses the materials identification on the certificates against the materials marking. It is also necessary to check these with the gas circuit breaker drawing datasheet, material list and other specifications as appropriate.

Visual inspection for surface finish and probable defects is done and dimensional compliance with specification need to be controlled, as well.

When the third party inspector carries out the material inspection, then provides the inspection visit report (IVR), the report contains the following items:

  • Confirmation of satisfactory document review
  • Record of the endorsement of certification reviewed/witnessed
  • Record of all non-conformities
  • Record of any tests witnessed and the result

Third Party Inspection for Gas Circuit Breaker - Construction

When the gas circuit breaker raw material inspection is carried out, and the results were satisfactory or non-conformities were closed by remedial action, then the gas circuit breaker manufacturer will start fabrication.

The third party inspector checks the following points on the gas circuit breaker, based on the inspection and test plan (ITP), which has already been agreed upon between the purchaser and the gas circuit breaker manufacturer.

The inspection scope is determined in the ITP. Some purchasers prefer to have stringent controls and assign the TPI for more “hold or witness points” for inspection and test activities, and some others prefer less “hold or witness points” and assign the TPI much more work in the “review document.”

This depends in the inspection budget, which purchasers assign for inspection. Much more inspection will have a much larger cost and less risk, and conversely, less inspection will have less cost but more risks.

For more details, review the Inspection and Test Plan for Gas Circuit Breaker article. There is a draft of the ITP in this article, which we believe is the best practice for gas circuit breaker inspection.

The third party inspector checks following items in Gas Circuit Breaker construction process:

  • Paint using specified colour swatch, thickness measurement, if specified
  • Name plate control
  • Outline dimensions, interface dimensions, bus bar dimensions and Clearances and other specified dimensions
  • Tightness/torque of terminals
  • Degree of protection

It is necessary the results meet drawings and applicable standards.

If the third party inspector is not in the hold or witness point in the ITP for this inspection stage, then he/she will review the gas circuit breaker manufacturer quality control report in his/her coming visit or on the final inspection day.

Third Party Inspection for Gas Circuit Breaker - General Arrangement Check

The third party inspector checks that all instruments, control switches, interlocks etc. are correctly rated and are correctly located, with specified labelling in accordance of approved drawings.

Third Party Inspection for Gas Circuit Breaker - Pressure Test

Air pressure is raised until the safety valve operates and this pressure is applied to all parts of the system and blow out pressure need not be more than specified value

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection stage, then he/she will review the gas circuit breaker manufacturer quality control report in his/her coming visit or on the final inspection day.

Third Party Inspection for Gas Circuit Breaker - Leakage Test

Systems containing gas under pressure is given leakage test to ensure against gas leakage at joints and it is necessary the result to be within specified value.

Third Party Inspection for Gas Circuit Breaker - Stored Energy System Test

The third party inspector checks the operation of air pressure switch and the number of close, open operations; starting at normal working pressure without replenishing the air in the air reservoir.

The test would be acceptable is the abnormality not occurs during the test.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection stage, then he/she will review the gas circuit breaker manufacturer quality control report in his/her coming visit or on the final inspection day.

Third Party Inspection for Gas Circuit Breaker - Power Frequency Voltage Dry Tension Test

The test is made on complete circuit. Test voltage, frequency and applied time must comply with the standard, code and/or specification.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection stage, then he/she will review the gas circuit breaker manufacturer quality control report in his/her coming visit or on the final inspection day.

Third Party Inspection for Gas Circuit Breaker - Voltage Test on Control and Auxiliary Circuit

All circuits of auxiliary and control circuit are subjected to the specified voltage for one minute. The test voltage is 1500V or 2000V, frequency 50HZ or 60HZ and applied time – 60 seconds.

The test would be acceptable if the circuit withstood to meet requirement.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection stage, then he/she will review the gas circuit breaker manufacturer quality control report in his/her coming visit or on the final inspection day.

Third Party Inspection for Gas Circuit Breaker - Main Circuit Resistance Test

The resistance of each pole of the main circuit is measured within factory limitation.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection stage, then he/she will review the gas circuit breaker manufacturer quality control report in his/her coming visit or on the final inspection day.

Third Party Inspection for Gas Circuit Breaker - Mechanical Operation Test

The adjustment and operation over the entire range of control voltage and specified operating pressure is controlled. The test is done in following conditions:

  • At specified maximum supply voltage and/or pressure at five opening and closing operations
  • At specified minimum supply voltage and/or pressure at five opening and closing operations
  • At rated supply voltage and/or pressure at five close-open and five open-close operation cycles

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection stage, then he/she will review the gas circuit breaker manufacturer quality control report in his/her coming visit or on the final inspection day.

Third Party Inspection for Gas Circuit Breaker - Timing Test (Operating Test)

The time required for breakers or components to operate on open, close, close-open and reclosing operation are checked and test would be acceptable if no abnormality occurs during the test.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection stage, then he/she will review the gas circuit breaker manufacturer quality control report in his/her coming visit or on the final inspection day.

Third Party Inspection for Gas Circuit Breaker Compressor Operation Test

Air compressor unit is operated electrically and its operation checked and would be acceptable if no abnormality occurs during the test.

Similarly, If the third party inspector is not in the hold or witness point in the ITP for this inspection stage, then he/she will review the gas circuit breaker manufacturer quality control report in his/her coming visit or on the final inspection day.

Third Party Inspection for Gas Circuit Breaker - Reporting

The third party inspector provides an Inspection Visit Report (IVR) after each visit, as well as a final report summarizing the activities carried out during the gas circuit breaker production in accordance with the contract requirements and circulated within the time limits specified in the contract.

The report is in the format required by the client and clearly indicates final acceptance or rejection of the gas circuit breaker.

Third Party Inspection for Gas Circuit Breaker - Release Note

When required by the contract or purchase order, a release note is issued by the third party inspection agency and given to the manufacturer when the gas circuit breakers have been accepted.

Third Party Inspection for Gas Circuit Breaker - Packing, Marking and Shipping:

The following points are checked by the third party inspector:

  • Verify that the packing materials conform to specifications and accepted practice for the mode of transport.
  • Verify protection against humidity, abrasion, distortion and other damage.
  • Verify shipping marks to marking instructions and record.
  • Verify handling marks.

Related Articles:

Third Party Inspection for Generator, Third Party Inspection for Power Transformer, Third Party Inspection for Power Cable, Third Party Inspection for Induction Motor, Third Party Inspection for Insulator, Third Party Inspection for Battery Charger, Third Party Inspection for UPS Storage Battery, Third Party Inspection for Control Panel, Third Party Inspection for Bus Duct, Third Party Inspection for SwitchgearThird Party Inspection Services, Third Party Inspection Agency, Third Party Quality Inspection, Third Party Independent Inspection


Return from Third Party Inspection for Gas Circuit Breaker to Third Party Inspection

Return from Third Party Inspection for Gas Circuit Breaker to Inspection for Industry Home


New! Comments

Have your say about what you just read! Leave me a comment in the box below.