Inspection and Test Plan for Generator

The inspection and test plan for generator article provides you information about generator test and generator inspection in manufacturing shop. The draft Inspection and test plan provided as well.

2 Free CPD Hours Courses - Completely Free

Enroll, Watch the Video, Take the Test, Download Your Cert and Submit to the API . 2 free courses are availble each with 2 hours credit. (Total 4 hours) - 1) ASME V Articl II , 2) ASME V Article 6 & 7 

Sample Inspection and Test Plan for Generator 

Download the tabulated format of the Generator Inspection and test plan.

You may need to review this sheet in conjunction of Third Party Inspection for Generator article.

Click following link if you need to review general definition for Inspection and Test Plan.

Inspection and Test Plan

The IEC, ISO standard requirements normally are applied for inspection and test plan in induction motor manufacturing shop.

The witness of some inspection and test by third party inspector is mandatory and cannot be waived.

Some others must only monitored and fully witnessing are not necessary, for these thing, the inspection man-days etc. depends to the purchaser decision, some prefer stringent monitoring and even assign resident inspector in manufacturing shop and some others relay to quality control system of the manufacture and assign only few days for monitoring points.

These are some of inspection points which need to be witnessed, checked, monitored and reviewed by third party inspector in Generator manufacture shop.

Important Points

  • Visual and dimensional check
  • Dielectrically and insulation test
  • Measurement and calculation of characteristics
  • Temperature rise test
  • Noise and vibration measurement
  • Hydrostatic test of mechanical equipment
  • Mechanical running test (vibration, noise, performance)
  • Operation of circuit breaker
  • Check of protection and synchronization devices