This content provide you with a sample instrument panel inspection and test plan, gauge board and desk ITP. This is a draft ITP and you need to modify it to meet your purchase order specification and requirements.
Instrument Desk Inspection and Test Plan Task | Vendor | TPI Inspection | Client |
---|---|---|---|
Material Test Certificate | H | W | R |
Performance test | H | H | R |
Insulation resistance test | H | W | R |
Final visual / Dimension Inspection | H | W | R |
Documentation review prior to release(Final activity of Technical Inspection) | H | H | R |
Pre-shipment Inspection by Third Party Inspector | H | H | R |
Instrument Panel and Gauge Board
Gauge Board and Instrument panel Inspection and Test Plan | Vendor | TPI Inspection | Client |
---|---|---|---|
Material Test Certificate | H | W | R |
Visual inspection including the following items as minimum: 1) Check painting, 2) Check run numbers and wire numbers for field connection, 3) Check for each item number, 4) Check for accessibility at rear of instruments and at back of panel mounted equipment, 5) Check wiring for colors, sizes and physically for electrical separation between signal/alarm/power wiring, etc., 6) Check electrical earting points and wiring insulation | H | W | R |
Pressure test | H | H | R |
Pneumatic test | H | H | R |
Performance test | H | H | R |
Functional test on all instrument loops | H | H | R |
Point to Point check of all electrical and pneumatic circuit as near to working conditions as can be simulated on every item of equipment | H | H | R |
Insulation resistance test | H | W | R |
Final visual / Dimension Inspection | H | H | R |
Documentation review prior to release(Final activity of Technical Inspection) | H | H | R |
Pre-shipment Inspection | H | H | R |
H: Hold Point implies that relevant production activities shall not proceed until the continuation of work is permitted by Purchaser. (Notification req'd)
W: Witness point implies that Purchaser intends to witness the designated inspection feature. If Purchaser decides not to witness the relevant feature, production can proceed without permission of Purchaser. (Notification req'd)
R: Review inspection & test records (Notification not req'd)
You may also review inspection and test plan for control panel article. There is more detail ITP there. You can also review third party inspection for control panel article.
This is a draft ITP and you need to add some more columns to identify your construction code, acceptance criteria and verifying documents.
Return from Instrument Panel Inspection and Test Plan to Inspection and Test Plan
Return from Instrument Panel ITP to Inspection for Industry Home
Did you find this article useful? Click on below Like button!
|
New! Comments
Have your say about what you just read! Leave me a comment in the box below.