This article provides information about vendor quality control plan, which is generated by material or equipment manufacturers. This plan collects all inspections and tests requirements from construction codes and standards and summarizes them in the simple table.
The quality control plan is very similar to the inspection and test plan, but it is normally a little more detailed than the inspection and test plan.
The purchaser submits the inspection and test plan to the vendor. This plan is general, and in return, the vendor would submit the quality control plan, which is in greater detail.
Then the vendor would prepare the quality control plan in a such way as to meet the requirements of the inspection and test plan. This plan must be prepared based on the Instruction of Vendor Quality Control Manual.
There is a frequently asked question about this QC Plan: When the purchaser submits the inspection and test plan, why it is necessary that the vendor prepare and submit the quality control plan?
The answer: In most cases, the inspection and test plan is general, because the purchaser might not be aware of the details of the design and the characteristics of the equipment, and it is necessary that the vendor goes through the details and provides more information about the inspections and tests.
Take for example a purchaser who submits an inspection and test plan to the centrifugal pump vendor and mandates for the witnessing of performance tests by a third party inspector.
So regarding to the design and characteristics of the pump, the vendor wants to do the performance test with specific method or in several steps, so all of these steps and process would be stated in the vendor QC Plan.
So this why it is necessary that the QC plan to be submitted by the vendor.
There is another alternative that is sometimes used by purchasers. They do not submit the inspection and test plan and ask the vendor to submit them the QC Plan; then they would comment or endorse the vendor QC Plan, which also would be considered the inspection and test plan.
Each activity in the quality control plan would have its own specific forms, which would need to be completed and signed by quality control personnel and endorsed by a third party inspection agency.
I4I Academy provides Quality Control Training Program.
You may review the Quality Control Forms article for more information.
This website covers the quality control and inspection guides for all major mechanical and electrical equipment; you may review the following articles for more information.
These are prepared as guidelines for third party inspection, but can be used for quality control as well.
There are draft inspection and test plans in each page; you can download the draft sheet and study the quality control task for each equipment type.
The first column shows the responsibility of manufacturer quality control.
Fix Equipment Inspection and Test Plan
Water Tube Boiler, Fire Tube Boiler, Shell and Tube Heat Exchanger, Fin Tube Heat Exchanger,Pressure Vessel, Storage Tank, Line Pipe, Steel Structure, Valve, Fire Alarm System,Fire Extinguisher, Flange, Fitting, Pipe, Hydrant, Paint, Bolt and Nut, Gasket, Tube, Insulation,Welding Electrode, Gasket, Strainer, Sample cooler, Steam Trap, Pipe Support, Expansion Joint
Rotary Equipment Inspection and Test Plan
Centrifugal Compressor, Reciprocating Compressor, Centrifugal Pump, Gas Turbine, Steam Turbine,Fan and Blower
Electrical Equipment Inspection and Test Plan
Generator, Power Cable, Induction Motor, Switchgear, Electrical Insulator, Gas Circuit Breaker,Control Panel, Battery Charger, UPS Storage Battery, Power Transformer, Bus Duct
Instrumental Equipment Inspection and Test Plan
Analyzer, Field Control System, Control Valve, Displacer Type Level Transmitter, Electromagnetic Flow Meter, Emergency Shutdown System, Float Type Level Switch, Gas and Flame Detector,Glass Gauge, Instrument Panel and Gauge Board, Junction Box, Mass Flow Meter,Motor Operated Valve, Orifice Plate and Flange, Pitot Tube, Pressure Gauge, Pressure Switch,Rupture Disc, Ultrasonic Flow Meter, Venturi Tube, Vortex Flow Meter
As you see the manufactures industrial quality control systems in all parts and sections are in “Hold Point” but only few items for purchaser inspector is in the “Hold Point”.
Other Related Articles:
Contractor QC Plan, Quality Control Manuals for Contractors, Quality Control Manual, Third Party Inspection, Pre-Shipment Inspection, Goods Inspection, Factory Acceptance Test, Shop Inspection, Vendor Inspection, Commodity Inspection, Vendor Inspection Services, Goods Inspection Services, Commodity Inspection Services, Pre-Shipment Inspection Services, 3rd Party Shop Inspection, Third Party Inspection for Material Stamp, Third Party Inspection Expediting
Return from Quality Control Plan to IndustrIal Quality Control
Return from Quality Control Plan to Inspection for Industry Home
Did you find this article useful? Click on below Like button!
|
New! Comments
Have your say about what you just read! Leave me a comment in the box below.