Vortex Flow Meter Inspection and Test Plan | Vortex Flow Meter ITP

This content provides you with a Vortex Flow Meter inspection and test plan. This is a draft vortex flow meter ITP and you must edit it to be fit for your purchase order specifications.

Vortex Flow Meter Inspection and Test Plan TaskVendorTPI InspectionClient
Vortex Flow Meter mill test certificatesHRR
Vortex Flow Meter mill test certificatesHRR
Vortex Flow Meter Pressure testHWR
Vortex Flow Meter Calibration checkHWR
Vortex Flow Meter Performance test including: hysterisis, sensitivity and reliability checkHWR
Vortex Flow Meter Insulation resistance testHWR
Vortex Flow Meter Final visual / Dimension InspectionHHR
Vortex Flow Meter Documentation review prior to release(Final activity of Technical Inspection)HHR
Vortex Flow Meter Pre-shipment InspectionHHR

Vortex Flow Meter Inspection and Test Plan Points

H: Hold Point implies that relevant production activities shall not proceed until the continuation of work is permitted by Purchaser. (Notification req'd)

W: Witness point implies that Purchaser intends to witness the designated inspection feature. If Purchaser decides not to witness the relevant feature, production can proceed without permission of Purchaser. (Notification req'd)

S: Witness, but spot check basis. Initial operation will be witness point and subsequent operation will be witnessed at discretion of Purchaser considering the results of previous inspection. (Notification not req'd : Randam Inspection)

R: Review inspection & test records (Notification not req'd)

General Note:

1) Vortex Flow Meter Witness/hold point by Code Inspector, when applied by Code /Local Regulation, is to comply with its requirements and to specify in Vendor's ITP.

2) Type of Inspection by Vortex Flow Meter Purchaser may be changed according to equipment criticality and vendor QC evaluation at job stage.

3) When requested in the requisition, detailed Vortex Flow Meter  ITP shall be submitted by Vendor.

4) Monitoring/Observation of Vortex Flow Meter Vendor shop daily routine works (i.e. Storage of materials, Adherence to approved procedures, Testing tool calibration check, workmanship, cleanliness and etc.) shall be done by Purchaser during inspection visit.

5) Vortex Flow Meter 100% inspection which is covered by the combination of witness / spot check / record review inspection & tests listed above and vendor's original QC activity shall be confirmed by Purchaser's inspector prior to shipment.

6) Unless otherwise specified in REQ., the Vortex Flow Meter sampling Q'ty of " S (Spot Witness Check) " shall be as follows:

3 to 20→3Pcs(all if total 2 and less) , 21 to 50→5Pcs, 51 to 100→10Pcs,101 to 200→20Pcs, 201 to 300→30Pcs, 301 to 500→50Pcs

Minimum 25 pcs or more of the commodity shall be arranged for H/W/S inspection and test at one time inspector's visit as much as practical.

7) Vortex Flow Meter Final Visual Inspection/Documentation Review/Pre-Shipment Inspection may Pre be combined within one time visit.