API 1169 Sample Flashcards
Try the 6 interactive sample flashcards below to experience how I4I Academy flashcard practice works. It’s the same portal format—scenario-based prompts that often require linking multiple requirements, followed by the answer and exact reference numbers so you can verify and learn quickly. Click a card to flip it, then click again to return to the prompt and keep drilling the concepts.
API 1169 – Interactive Flashcards (Practice Mode)
Click a card to reveal the answer and reference numbers. Click again to flip back.
Flashcard 1 • Field Bending Cross-Table
Cold weather bending: what must be confirmed AND verified?
A crew starts field bending during a cold snap. Which requirement appears as a pre-work confirmation and also must be checked during ongoing monitoring?
Answer: Confirm the operator’s ambient temperature limits for bending are identified before work, and verify those limits are adhered to during cold conditions while monitoring.
Ref: API 1169 Annex A Table A.50 & Table A.53
Flashcard 2 • Monitoring vs Daily Report
What you monitor is not always what you report
For field bending, name one item that is a monitoring/check requirement and one item that is explicitly listed as daily reporting content.
Answer: Monitoring/check examples include specified angle requirements, bend radius limitations (including coating limitations), and limits of ovality/wall thinning. Daily reporting examples include start/end chainages or station numbers for bending/set-up, locations where pipe was not bent and reasons, and number/types of bends made.
Ref: API 1169 Annex A Table A.53 & Table A.54
Flashcard 3 • Lowering-In Categories
Which lowering-in category protects coating from trench hazards?
During lowering-in, the inspector focuses on preventing damage from rock/construction debris and trench-bottom hazards. Which checklist category does this fall under, and where is it detailed?
Answer: It falls under the “Trench Base Preparation” item listed within the lowering-in monitoring checklist, and the detailed checks are provided in the referenced trench-base table.
Ref: API 1169 Annex A Table A.87 & Table A.92
Flashcard 4 • Buoyancy Control (Monitor + Report)
What must be recorded, and what shows up in the daily report?
For buoyancy control during lowering-in, what information must be monitored/recorded in the field, and what matching information is expected in the daily lowering-in report?
Answer: Monitor/record buoyancy control start/stop locations and type. The daily lowering-in report can include buoyancy control types, locations, and start/stop locations.
Ref: API 1169 Annex A Table A.95 & Table A.96
Flashcard 5 • HDD Top-Level Checklist Links
HDD monitoring: list the linked categories
The HDD installation monitoring checklist points you to multiple tables. What are the top-level categories you must cover, and where are those category tables referenced?
Answer: Prior to commencing work, safety, environmental considerations, and general horizontal directional drilling operations. These top-level categories are listed in the HDD monitoring checklist and each points to its own table.
Ref: API 1169 Annex A Table A.98 (refs Table A.100, A.101, A.102, A.103)
Flashcard 6 • Reporting Separation (Two Report Types)
CP/test station vs third-party crossing report
A crew is documenting a third-party crossing and also completing CP/test station work. Which items belong specifically in the third-party crossing report, and which item belongs in the CP/test station report?
Answer: Third-party crossing report includes the name of third-party pipeline companies, pipe-to-soil readings at the crossing, and distance from the nearest third-party rectifier. The continuity test results upon backfilling (to confirm test leads have not broken) are associated with the CP/test station reporting context.
Ref: API 1169 Annex A Table A.133