Conveyor Inspection and Test Plan

This content provides you with a sample Conveyor Inspection and Test Plan. You must change this Conveyor ITP to meet your purchase order specifications.

Conveyor ITP TaskVendorTPI InspectionClient
Conveyor Pre-inspection meeting, when specified by PurchaserHHR
Material Conformance CertificateHRR
Test for MotorHWR
Temporary Assembly and Preassembly (Partial)HWR
Visual InspectionHWR
Dimensional InspectionHWR
No Load Test (Drive Unit Only)HWR
Insulation Resistsance and High Voltage Test for Power/Control CabinetsHWR
Functional/Sequence Test for Control Circuits Including PLCHHR
Final visual inspection (includ Painting, coating, preservation, lining, picking, nameplate, tagging, marking, Auxiliary items like spare parts, bolts,etc.)HHR
Documentation review prior to release(Final activity of Technical Inspection)HHR
Pre-shipment InspectionHHR

Conveyor Inspection and Test Plan Points

H: Hold Point implies that relevant production activities shall not proceed until the continuation of work is permitted by Purchaser. (Notification req'd)

W: Witness point implies that Purchaser intends to witness the designated inspection feature. If Purchaser decides not to witness the relevant feature, production can proceed without permission of Purchaser. (Notification req'd)

S: Witness, but spot check basis. Initial operation will be witness point and subsequent operation will be witnessed at discretion of Purchaser considering the results of previous inspection. (Random Inspection : Notification not req'd)

R: Review inspection & test records (Notification not req'd)

General Note :

1) Conveyor Witness/hold point by Code Inspector, when applied by Code Stamp/Local Regulation, is to comply with its requirements and to specify in Vendor's ITP.

2) Type of Inspection by Conveyor Purchaser may be changed according to equipment criticality and vendor QC evaluation at job stage.

3) When requested in the requisition, detailed Conveyor ITP shall be submitted by Vendor.

4) Monitoring/Observation of Conveyor Vendor shop daily routine works (i.e. Storage of materials & welding consumables, Adherence to approved procedures, Testing tool calibration check, Welder/NDE Operator performance & qualification, workmanship, cleanliness and etc.) shall be done by Conveyor Purchaser during inspection visit.

5) Final Conveyor Visual Inspection/Documentation Review/Pre-Shipment Inspection may be combined within one time visit.