This article provides you a electromagnetic flow meter inspection and test plan. This is a draft ITP and you need change it to meet your purchase order specification and requirements.

Electromagnetic Flow Meter Inspection and Test Plan TaskVendorTPI InspectionClient
Electromagnetic Flow Meter Checking of characteristics including the following items as minimum: body and connectionHWR
Electromagnetic Flow Meter Mill test reportsHRR
Electromagnetic Flow Meter Non-destructive examination, when specifiedHRR
Electromagnetic Flow Meter Pressure testHHR
Electromagnetic Flow Meter Performance test including: calibration and hysteresisHHR
Electromagnetic Flow Meter Insulation resistance testHWR
Electromagnetic Flow Meter Visual / Dimension InspectionHHR
Electromagnetic Flow Meter Documentation review prior to release(Final activity of Technical Inspection)HHR
Electromagnetic Flow Meter Pre-shipment InspectionHHR

Electromagnetic Flow Meter Inspection and Test Plan Points

H: Hold Point implies that relevant production activities shall not proceed until the continuation of work is permitted by Purchaser. (Notification req'd)

W: Witness point implies that Purchaser intends to witness the designated inspection feature. If Purchaser decides not to witness the relevant feature, production can proceed without permission of Purchaser. (Notification req'd)

S: Witness, but spot check basis. Initial operation will be witness point and subsequent operation will be witnessed at discretion of Purchaser considering the results of previous inspection. (Notification not req'd : Randam Inspection)

R: Review inspection & test records (Notification not req'd)

General Note :

1) Electromagnetic Flow Meter Witness/hold point by Code Inspector, when applied by Code /Local Regulation, is to comply with its requirements and to specify in Vendor's ITP.

2) Type of Inspection by Electromagnetic Flow Meter Purchaser may be changed according to equipment criticality and vendor QC evaluation at job stage.

3) When requested in the requisition, detailed Electromagnetic Flow Meter ITP shall be submitted by Vendor.

4) Monitoring/Observation of Electromagnetic Flow Meter Vendor shop daily routine works (i.e.Storage of materials, Adherence to approved procedures, Testing tool calibration check, workmanship, cleanliness and etc.) shall be done by Purchaser during inspection visit.

5) 100% Electromagnetic Flow Meter inspection which is covered by the combination of witness / spot check / record review inspection & tests listed above and vendor's original QC activity shall be confirmed by Purchaser's inspector prior to shipment.

6) Unless otherwise specified in REQ., the Electromagnetic Flow Meter sampling Q'ty of " S (Spot Witness Check) " shall be as follows:

3 to 20→3Pcs(all if total 2 and less) , 21 to 50→5Pcs, 51 to 100→10Pcs,101 to 200→20Pcs, 201 to 300→30Pcs, 301 to 500→50Pcs

Minimum 25 pcs or more of the commodity shall be arranged for H/W/S inspection and test at one time inspector's visit as much as practical.

7) Final Electromagnetic Flow Meter Visual Inspection/Documentation Review / Pre-Shipment Inspection may be combined within one time visit.