API 1184 Sample Questions

Test your API 1184 knowledge with 10 interactive sample practice questions. This module matches the practice-mode experience in the I4I Academy question bank—after you select an answer, you’ll immediately see whether it’s correct along with the corresponding API 1184 section reference so you can verify the requirement and learn more efficiently. For multi-select questions, choose all that apply, then click Check Answer to view your results and references.

API 1184 Training Course Sample Questions (Interactive)

Mixed format: some questions are single-choice (instant feedback), and some are multi-select (choose all that apply, then click Check Answer). Scoring is based on your first attempt only.

Q1. During stormwater management facilities construction, which item is specifically a reporting requirement (not a monitoring/verification item)?

  • ❌ Incorrect. Correct Answer: C
    Ref: API 1184 Table 51 & Table 52
  • ❌ Incorrect. Correct Answer: C
    Ref: API 1184 Table 51 & Table 52
  • ✅ Correct. Correct Answer: C
    Ref: API 1184 Table 51 & Table 52
  • ❌ Incorrect. Correct Answer: C
    Ref: API 1184 Table 51 & Table 52

Q2. (Select ALL that apply) Which items are explicitly part of hydrostatic testing readiness steps covering preparation and winter conditions?

Q3. Which documentation item appears as a monitoring step in test head removal/replacement and is also explicitly listed as a reporting requirement?

  • ❌ Incorrect. Correct Answer: B
    Ref: API 1184 Table 134 & Table 136
  • ✅ Correct. Correct Answer: B
    Ref: API 1184 Table 134 & Table 136
  • ❌ Incorrect. Correct Answer: B
    Ref: API 1184 Table 134 & Table 136
  • ❌ Incorrect. Correct Answer: B
    Ref: API 1184 Table 134 & Table 136

Q4. (Select ALL that apply) Which items are explicitly called out in hydrostatic testing reporting requirements, rather than being a drying-method monitoring check?

Q5. Which action is performed after backfill to confirm integrity and is also specifically captured as a reported test result?

  • ❌ Incorrect. Correct Answer: B
    Ref: API 1184 Table 142 & Table 143
  • ✅ Correct. Correct Answer: B
    Ref: API 1184 Table 142 & Table 143
  • ❌ Incorrect. Correct Answer: B
    Ref: API 1184 Table 142 & Table 143
  • ❌ Incorrect. Correct Answer: B
    Ref: API 1184 Table 142 & Table 143

Q6. (Select ALL that apply) Which items directly address avoiding shorts/broken continuity/unintended bonding across cathodic protection installation controls and grounding considerations?

Q7. Which activity is the one where API 1184 explicitly calls out thermite device safety and also expects monitoring of thermite weld workmanship?

  • ✅ Correct. Correct Answer: A
    Ref: API 1184 Table 141 & Table 142
  • ❌ Incorrect. Correct Answer: A
    Ref: API 1184 Table 141 & Table 142
  • ❌ Incorrect. Correct Answer: A
    Ref: API 1184 Table 141 & Table 142
  • ❌ Incorrect. Correct Answer: A
    Ref: API 1184 Table 141 & Table 142

Q8. (Select ALL that apply) Which are test report deliverables (not progress reports)?

Q9. Which pair of safety controls is explicitly shown in both the building lighting inspection inputs and the AC electrical systems safety concerns?

  • ❌ Incorrect. Correct Answer: B
    Ref: API 1184 Table 176 & Table 185
  • ✅ Correct. Correct Answer: B
    Ref: API 1184 Table 176 & Table 185
  • ❌ Incorrect. Correct Answer: B
    Ref: API 1184 Table 176 & Table 185
  • ❌ Incorrect. Correct Answer: B
    Ref: API 1184 Table 176 & Table 185

Q10. (Select ALL that apply) Which statements are true for both building lighting monitoring and cathodic protection monitoring sections in API 1184?

Your Score (First Attempt Only)

Score is based on the first answer you submit per question (first radio selection or first “Check Answer” click).


 